April 2018 - We are moving from The Dealership to IngenuityLabs at the Hamilton Collaborative.
Tasks remaining to be done:
Contain things into containersDisassemble shelves into whatever size needed for transportCall scrap hauling guy to haul away total junk we don't want. (still a ways off…)
PRIORITY OF STUFF TO MOVE
- Almost everything moved at this point
- Trash cans
- 2 chairs
- misc stuff - not much left
Things to do at Hamilton:
Clean up debris in corner of pod. PPE suggested.Paint right wall of podUse APC PDU to convert 240 to 120?Double-check the specs, and it would likely need some kind of extension cord to access outlet on the ceiling (estimated budget for 30' cord - ~$100, probably a little under that)- Probably not - Max voltage input on the “PDU” is 230V, service is 240v. If service was 208V we'd be in business.
Get a generator cable to split the 240 to 2×120 - costs about $35.- Replace fluorescent light with LED (budget: $40/each for 3200 Lumen units)
- Plan B- replace fluorescent tubes w/LED Drop-in replacements($7-10 each)
pour concrete where the boards cover the void in the floor? Is that allowed?- Run ethernet cable to Soulcraft/AO router - coordinate before plugging anything in…
- A stepstool/short ladder to reach shelf tops? We'll have to better utilize shelf top space - no more empty boxes lining the shelves if we can help it…
- Flooring? The floor in our pod is basically wood block. Cover it with something?
Timeline:
- Monday, 4/23-Friday, 4/27 - Sam is available all week for whatever is left
- Saturday, 4/28 - Shaker Makers?
- Sunday, 4/29 - Anything left?
- Tuesday, 5/1 - Deadline for everything out